EASTON, Pa. — The Easton Area School Board voted unanimously Tuesday to approve an architectural and engineering services agreement for a construction project that could lead to the construction of a new high school building.
The contracts are with Alloy5 LLC and D’Huy Engineering of Bethlehem.
The board raised the issue of a construction project last month, about a year after the board shelved the issue of a new high school.
On Jan. 30, the board voted to allow the district to move forward with the process.
Options presented to the board in April 2023 include building renovations, a hybrid concept of new construction and adaptive reuse or new construction.
The 378,000-square-foot high school is located on 81 acres along William Penn Highway and was last renovated in 2003.
The school has previously said that the existing buildings are insufficient to accommodate 3,000 students.
Last month, the administration strongly recommended building a new high school building at the current site of 2601 William Penn Highway.
The project’s initial budget is $190 million to $250 million.
Fees paid to architects and engineers will be based on the final cost of the project.
The agreement calls for the district to pay the fee on an hourly basis until a final budget is approved, at which time the fee will be fixed at no more than 5.7 percent of the construction cost.